back to blogs

Case Kemi Mine: Expansion of a switchyard as a comprehensive service

April 22, 2024    |     ASES

We started an expansion work of a 110 kV switchyard for ABB at Outokumpu Chrome Oy Kemi Mine this May. The objective is to improve service reliability and enable alternation during e.g. switchyard maintenance.

“The project was kicked off in mid-May with soil inspections. After that we began building the foundation, as well as a transformer spill container”, project manager and electrical work supervisor Veikko Karppinen tells about the first phase of the expansion work.

“At the end of June, the foundation was ready, and a building was installed on it. The building consisted of three modules that were pieced together onsite. After the building was finished in August, a 25 MVA main transformer was installed. The project’s final phase; cabling, coupling and testing is planned to be ready in October”, Karppinen continues.

 

kytkinkentänlaajennus

 

Scheduling plays a crucial role

“The whole project will be carried out as a comprehensive service, using our own subcontractors, which is the most effortless approach for our customer. By taking care of the project comprehensively from start to finish we can minimize variables and ensure staying on schedule”, concludes Karppinen.

Well-functioning schedules played a crucial role during the summer season, as the project will be finished and the switchyard in use during October.

MORE POSTS

A large investment in Kokkola employs ASES in the field of process electrification

February 9, 2024
A major industrial investment project is underway in Kokkola, as the Sibanye-Stillwater’s Keliber lithium refinery is being built in the Kokkola Industrial Park. ASES will carry out the process electrification installations for th...

Read More

Case Outokumpu – Extensive project entity in process electrification of the Deep Mine project

October 21, 2022
In the Deep Mine project of the Outokumpu Kemi mine, the mine will be deepened between 500 and 1000 levels as an underground mine. A lot of infrastructure required by the mining process has been built underground, and ASES has pla...

Read More

Ases and Siemens Energy Oy in cooperation: modernization of high-voltage switchgear

September 17, 2021
ASES and Siemens Energy Oy have jointly implemented two extensive 110 kV gas-insulated switchgear (GIS) modernization projects. Siemens Energy Oy has been the main contractor and ASES has done high-quality installation work in the...

Read More

Ases & South-West Supply in cooperation: recovering the waste energy of Terrafame hydrogen plants

June 17, 2021
ASES and South-West Supply Oy have implemented new heat recovery solutions for Terrafame's hydrogen plants, achieving significant savings in energy use and reducing carbon dioxide emissions. Two sites were identified in the projec...

Read More
 
DJI_0690-ASES-HLPfi_kapea_t

VOIMMEKO OLLA AVUKSI?

Kuinka voimme auttaa?

Jätä viesti tai soita meille – keskustellaan yhdessä miten projektisi saadaan valmiiksi nopeasti ja kustannustehokkaasti.

Contact us
Tai soita meille: +358 40 555 3214